Project Details
Location: Fleetsbridge, Poole
Customer: Mulberry Construction Group Limited
Duration: Ongoing
Project Description
This new construction consists of 2 brand new industrial units standing at 88,000 and 38,000 sq ft. In the pre hand over phase Boomdob was originally brought in by an external cleaning company to assist with sticker removal from newly installed glazing. The job took a day using our cherry picker, saving the client the hassle of hiring a separate machine and operator
While carrying out the sticker removal, Dob noticed that one set of first-floor windows were missing silicone pointing. He alerted the main contractor, Mulberry Construction Ltd, who immediately instructed Boomdob to carry out the remedial work. Although the space between the building and boundary was too narrow for direct access, this was no problem, with the long reach on our cherry picker Dob was able to complete the job quickly and safely from the next door carpark of the gym
Used to working on industrial units it also came to Dob's attention the glass canopies were yet to be installed above both entrances. With Dob's experience in commercial and industrial roofing and cladding and building envelope this was also something he could do. He arranged for a scissor lift and fitted two large glass canopies (six panels each). While on the lift, he also installed missing weep vents and glazing beads in the windows. Impressed by Dob’s initiative and capability, Mulberry’s Defects & Maintenance Manager (based in Leeds) began relying on Boomdob to handle and coordinate a wide range of tasks
Trusted To Deliver More
Dob soon became the Defects and Maintenance Manager's go to for all the remaining jobs that came up, saving him travelling back and forth from Leeds unnecessarily
He sourced and organised a number of other trades - a mastic man for work in the toilets and entrance areas, a tiler to install splashback tiling in the toilets and cleaning cupboards and a locksmith to change locks where keys were missing
Due to our cherry picker being electric it is also suitable for indoor use. Dob carried out a number of tasks inside including removing site debris trapped in the internal sheeting rails, repairing a bent sheet rail damaged by machinery and replacing a tie bar at approx. 10m high
We were also asked to install three external bat boxes to meet planning obligations and Dob later supported Mulberry on another project, repairing a damaged cladding door head at their Plumbase site
Mulberry Construction Group Limited
What impressed us most is the way Boomdob combines efficiency with problem-solving. He does not waste time yet never compromises on safety or quality. Whether it is defects and snagging or urgent remedial work, he approaches every task with the same level of care and precision. Another huge benefit of working with Boomdob is the flexibility he offers. Instead of having to hire multiple contractors we were able to get everything done quickly and effectively by relying on one highly skilled professional with his own equipment. Boomdob is more than just a cherry picker operator. His knowledge, adaptability, and hands-on approach have been invaluable, and I would have no hesitation in recommending him to any business or homeowner who needs work done at height. If you want peace of mind knowing the job will be done right first time, safely, and efficiently, then Ian is your first port of call. We look forward to continuing working with Ian in the future. The word in our office when something unexpected comes in is “Can Boomdob do it?” Give him a call!
With 30 years of experience in commercial roofing, cladding and building envelope, Dob is adept at handling your at height defects and snagging prior to handover as well as the 12 month period and remedials. With our own cherry picker we offer a unique 3 in 1 service providing the access, operator and labour. For expert defects, snagging and maintenance call Boomdob now for more information or a free, no-obligation quote